Create a Website Account - Manage notification subscriptions, save form progress and more.
The City is in process of finalizing the preliminary engineering for the pedestrian improvements proposed for the Topping Road Phase 2A (Topping Estates to Old Colony).
An open house will be held to provide information on the proposed improvements. The open house is scheduled for Wednesday, August 10th from 4PM to 6PM at the Municipal Center.
This meeting will be an open-house format. Maps and other detailed project information will be available. Participants are welcome to submit verbal and written comments during the open house, as well as ask the project team about the plans for the project.
If you have any questions regarding the project or open house, please contact Michael Zeltmann at (314) 587-2824 or ZeltmannM@town-and-country.org.
Milestone Description | Start Date | End Date |
---|---|---|
Topping Road Phase 1 | 11/08/2021 | 05/26/2022 |
Place bulletin board & bring in construction equipment | 11/08/2021 | 11/09/2021 |
Site System Landscaping install all erosion control devices | 11/08/2021 | 11/09/2021 |
Metron Surveying to complete surveying and staking | 11/08/2021 | 11/10/2021 |
Removal of trees / shrubs / brush | 11/10/2021 | 11/12/2021 |
Complete work road widening at Clayton & Topping | 11/10/2021 | 11/13/2021 |
Complete work on storm sewer items | 11/15/2021 | 12/15/2021 |
Gerstner Electric to work on signal items | 11/20/2021 | 03/05/2022 |
Work on sidewalk and grading items (start at Clayton Road) | 11/20/2021 | 03/05/2022 |
Stop calendar day count per agreement | 12/05/2021 | 03/05/2022 |
Complete remaining work on concrete items | 03/05/2022 | 03/10/2022 |
D&S Fence to install guardrail / fence / handrail items | 03/10/2022 | 03/20/2022 |
Site System Landscaping to complete work on landscaping items | 03/22/2022 | 04/01/2022 |
Clean up job / prep for milling and paving of Topping Road | 04/04/2022 | 04/09/2022 |
Milling and paving of Topping Road | 04/11/2022 | 04/16/2022 |
Remove erosion control items | 04/18/2022 | 05/02/2022 |
Clean up job / semi-final inspection | 05/05/2022 | 05/07/2022 |
Punch list items | 05/07/2022 | 05/09/2022 |
Final inspection / job is complete | 05/12/2022 | 05/15/2022 |
The City has received authorization to advertise for construction on Topping Road Phase I, and anticipates a start to construction in September 2021. Work will include signal upgrades at Topping & Clayton, storm sewer work, a 5 foot concrete sidewalk installation from Clayton to Topping Estates, and repaving of Topping from Clayton to Fiddle Creek Lane. Staff anticipates the project will take roughly 90 days to complete and during construction there will be delays and periodically lane closures. Questions or concerns throughout the project can be directed to the Planning & Public Works Department at (314) 587-2820.
Schedule |
---|
September 2012, Ordinance 3695 authorizes Topping Road Programming study |
February 2013, Board approved Resolution R03-2013 authorizing first grant application |
January 2015, Board approved Resolution R03-2015 authorizing second grant application for Phase 1 |
February 2016, Board approved Resolution R03-2016 authorizing third grant application for Phase 1 |
February 2017, Board approved Resolution R02-2017 authorizing grant application for Phase 1 |
September 2017, the grant was approved by East-West Gateway Council of Governments |
March 2018, Board adopts Ordinance 4176 approving program grant agreement with Missouri Highway and Transportation Commission |
May 2018, Topping Road Task Force appointed by Mayor Dalton with approval of the Board |
September 2018, Task Force interviewed engineering companies |
May 29, 2019, Topping Road Task Force presented with trail design options east/west configuration or mid-block crossings. The Task Force determines design recommendation on the west side configuration due to utilities and right-of way. |
Open House for residents held on June 18, 2019 |
Resident input was to reduce width of sidewalk from a 8 foot asphalt to a 5 foot concrete |
June 2019, City requests amendment to Agreement with East-West Gateway Council of Governments |
August 2019, Board approved Resolution R15-2019 to withdraw Phase 2 grant funding and proceed with a 5 foot sidewalk Phase 1 |
June 2020, City received authority from MoDOT for easement acquistion |
January 2021, City requests Right-of-Way Clearance Certification from MoDOT |
April 2021, Preliminary design plans submitted to MoDOT |
May 2021, Water main relocation work completed |
July 2021, MoDOT approved right-of-way clearance and authorization to bid |
Financials |
---|
November 2018, Board adopted Ordinance 4242 to contract with H.R. Green for $225,887 to provide engineering design following proposal review by Task Force |
October 2019, Board approved Supplemental Agreement #1 with H.R. Green for design change of scope for pavement Phase 2 and trail change to Phase 1 |
November 2020, Board authorizes easement acquisition and landscaping plans for total cost $54,280 ($120,000 was budgeted) at 50/50 match |
December 2020, proposed budget for fiscal year 2021 includes $1,589,500 to be reimbursed at 50%. $845,00 Road Fund, $544,500 Parks and Trails Fund, $200,000 Stormwater Fund, |
December 2020, Board adopted Ordinance 4407 with Horner and Shifrin to provide construction engineering and materials testing at 50/50 match |